QUESTION: 

 

2.1: Which of the following attributes relate to the project lifecycle? (PMT2ed p.37) 

a. The project is subdivided into phases. 

b. Each phase produces a distinct deliverable. 

c. Each phase repeats itself many times over the duration of the project 

d. Subdivide the project into work packages. 

 

2.1 Answer: A and B are correct. A and B are correct because the lifecycle subdivides the project into phases with a distinct deliverable. C is incorrect because the phases are not repeated, but sequential, and d is also incorrect because it is the WBS that subdivides the scope of work into work packages. 

 

 